This course is aimed to give, the installation of ventilation ststems and to gain the necassary capabilities for project,installation,start up,troubleshhoot and perfect running.
Prerequisite(s)
Course Code Course Name…
Corequisite(s)
Course Code Course Name…
Special Requisite(s)
70% attendance is required.
Instructor(s)
Lecturer Yavuz OKUMUŞ
Course Assistant(s)
Schedule
Tuesday, 13:00 - 16:00, Synchronous
Office Hour(s)
Tuesday 16:00, chat room
Teaching Methods and Techniques
lectures,discussion and application.
Principle Sources
1-handoust and notes given by lecturer
2*Modern Refrigeration and Air Conditioning
ANDREVV D. ALTHOUSE, B.S., (M.E.), M.A. CARL H. TURNQUIST, B.S., (M.E.), M.A. ,ALFRED F. BRACCIANO, B.S., M.Ed., Ed. Sp. Publisher THE GOODHEART-WILLCOX COMPANY, INC. Tinley Park, I, Copyright 2004, Library ot Congress Caialog Card Number 2003052840 ISBN-13: 978-1-59070-280-2 ISBN-10: 1-59070-280-8
William C. WhitmanWilliam M. JohnsonJohn A. TomczykEugene Silberstein
COPYRIGHT 2009.. ISBN 1-4283-1936-0,, delmar.cengage.com,, Printed in the United States of America 1 2 3 45 08 07 06 05 04
Course Schedules
Week
Contents
Learning Methods
1. Week
Introduction to Ventilation
Oral presentation
2. Week
Basic system elements of ventilation 1
Oral presentation,technical excursion
3. Week
Installation of the system elements.
Oral presentation and,application
4. Week
Manufacturing the ducts
Oral presentation and fieldwork
5. Week
Fans,fan's Laws,calculation of flow, and fan selection.
Oral presentation, projet,application and uygulama ve technical excursion
6. Week
Basic elements and accessories of ventilation systems.
Oral presentation,fieldwork and project
7. Week
Selection of the system elements of ventilation systems.
Oral presentation,fieldwork and project
8. Week
. Mechanical ventilation with air supply and exhaust; Determination of the outside airflow rate; Design of ventilation and air heating with or without air circulation.
Oral presentation,fieldwork and project
9. Week
Heat exchangers - Heaters; Coolers; Humidifiers
Oral presentation,fieldwork and project
10. Week
Air to air energy recovery equipment.
Oral presentation,fieldwork and project
11. Week
Air cleaners for particulate contaminants; Filtration of air.
Selection of the system elements of ventilation systems and project.
Oral presentation,fieldwork and project
12. Week
Space air diffusion - Air flow in rooms; Air terminal diffusers; Room air distribution equipment.
Oral presentation,fieldwork and project
13. Week
Duct design - airflow in duct, pressure losses.
Understanding Ventilation Projects and making simple projet.
Oral presentation,fieldwork and project
14. Week
Fire protection of ventilation systems.
Manufacturing the ducts and cuct calculations.
Oral presentation,fieldwork and project
15. Week
Final Exam
16. Week
Final Exam
17. Week
Final Exam
Assessments
Evaluation tools
Quantity
Weight(%)
Midterm(s)
1
30
Homework / Term Projects / Presentations
1
10
Attendance
1
10
Final Exam
1
50
Program Outcomes
PO-1
According to the needs of the market, to be trained in current technology
PO-2
When reading becomes a student earns money
PO-3
to solve basic math and physics problems which related to air conditioning
PO-4
pipe merge and setup simple electrical circuits and electrical controls, sensors and to make electric motor connections
PO-5
To make basic geometric drawings, to draw 2 and 3-dimensional circuit designs about air conditioning and refrigeration in computer-based programs
PO-6
They should be able to the installation of all the household and commercial refrigeration and heating systems
PO-7
they should be able to select heating, ventilation, air conditioning and refrigeration systems and design and installation cold room and other types
PO-8
They can make ventilation duct manufacturing, installation, and insulation, to select central HVACR system components and montage.
PO-9
They can mount to household, commercial and industrial HVACR systems and to install automatic control circuits and to develop some programs for control to this circuits.
PO-10
They can lay natural gas pipeline for buildings and make some tests for impermeability
PO-11
They can create the basis of the quality management system and apply statistical quality control methods
PO-12
They can take measures under the first-aid for job security and apply the basic principles of first aid
PO-13
They can apply information technology in their all works.
PO-14
They can establish and operate their businesses and manage company, manufacturing process, marketing, company’s budget and finance.
PO-15
They can teach and apply all design criteria, calculation methods, system selection methods for buildings and latest technological developments.
Learning Outcomes
LO-1
1)Selection of the ventilation system elements
LO-2
2) Installation of the ventilation system elements
LO-3
3-) Manufacturing of the ventilation systems ducts
LO-4
4) Installation of the ventilation systems ducts
LO-5
5)Isolation of the ventilation systems ducts
LO-6